May 21, 2012 Project Update

 

Ladys Island Park

  • Have Park sign designed, pending approvals
  • Park completed, expect opening in the month of June. 

 

Burton Wells Phase II

 

  • Park Completed
  • Grand opening was held 5/18

Buckwalter Park Soccer Field III

 

  • Field completed, available for use.

St. Helena Branch Library

  • Masonry Block work complete.
  • Stucco completed.
  • Structural wood framing complete.
  • Steel erection complete.
  • Flat surface roofing complete.
  • Standing seam roofing underway
  • HVAC, Electrical system, above ground plumbing, 70% complete.
  • Drywall underway.
  • Window frame installation underway.
  • Mid November 2012 completion date

DSN

  • Project accepted
  • Working with Attorney to complete project close out.
  • Received preliminary commissioning report, facility is performing well.

Contract 43 

  • Jasmine Hall – completed
  • Ballpark – completed
  • Middlefield Circle – completed
  • Stanley Road – on hold pending (ROW) right of way.

Contract 44

  • Jessica – completed
  • Ned Court – completed
  • Foreman Hill Road – construction is 90% complete
  • Fish Haul -- on hold pending (ROW) right of way.